Streambank Resiliency & Flood Study
Project Overview
Friends of the Wissahickon is undertaking a comprehensive study of Forbidden Drive and seven adjacent access trails in Wissahickon Valley Park. The findings will inform the next decade of resiliency-focused capital projects and will enable FOW to make informed, transparent decisions that balance environmental restoration and community desires.
The need for this study arises from ongoing stormwater management challenges that jeopardize water quality, trail safety, and recreational access. Since the 2017 Forbidden Drive Drainage System Assessment Report, which evaluated 417 incipient gullies and 28 series of drainage structures, Philadelphia Parks and Recreation, Philadelphia Water Department, and FOW have continued to document ongoing erosion and flooding issues.
On May 7th, 2026, FOW and Princeton Hydro hosted the first of two public meetings for this project. Read more here: “Meeting Recap: Where Do Our Trails Need the Most Work?”
Project Partners: Philadelphia Parks and Recreation, Philadelphia Water Department, Philadelphia County Planning Commission, Delaware Valley Regional Planning Commission
Consultant: Princeton Hydro
This project is made possible by the generosity of PA Department of Environmental Protection Coastal Zone Management.
Timeline
March 2026 – Project Kickoff
May 2026 – Study Public Meeting 1 & Survey Launched
June 2026 – Survey Closed & Engineer Field Assessments Begin
July 2026 – Engineer Field Assessments Continue
2027 – Public Meeting 2, Final Report, and Public Dissemination of Findings & Data